Mon–Fri 9:00–18:00 · online 24/7

Construction

Design

Equipment

Company

Client account

Submit requests, track their status, and receive estimates and contracts online.

Sign in or register +7 (727) 972 30 30

Special machinery rental: how to calculate the cost and avoid overpaying

Special machinery rental: how to calculate the cost and avoid overpaying

Equipment rental is one of the major cost items on a construction site: in earthworks and erection it can account for a noticeable share of the estimate. Proper planning makes it possible to cut these costs by tens of percent without losing pace — through accurate selection of machines, a well-thought-out schedule and an understanding of what exactly you are paying for.

8 hstandard shift in most contracts
4–8 htypical minimum order
up to 30%overpayment due to downtime and wrong selection (based on market experience)

What makes up the price

ComponentHow it is calculatedWhat to look out for
RatePer engine hour or per shift (usually 8 hours)Whether time is counted from leaving the base or from arrival on site
Minimum orderOften 4–8 hours, even if the job took one hourWhether several tasks can be combined into one order
MobilisationDelivery to the site and back; for heavy machinery — a low-bed trailerFixed amount or by mileage
OperatorUsually included in the priceWho is responsible for slingers, signallers and permits
DowntimeIf caused by the client, usually paid at the rateHow the start and end of downtime are recorded
FuelMore often included; for long-term rental — separatelyConsumption rate and refuelling procedure

Good to know Compare not the hourly rate but the total cost of completing the task: rate × actual time + mobilisation + possible downtime. A cheap machine that works twice as long ends up costing more.

How to match machinery to the task

Excess capacity costs more, while insufficient capacity disrupts deadlines. Below are guidelines for the main types of work; for current models and specifications, see the special machinery catalogue.

TaskSuitable machineryComment
Excavation for a private house, trenchesBackhoe loaderVersatile, quickly relocates under its own power
Large excavation, rocky soil22 t crawler excavatorHigh productivity, requires delivery by low-bed trailer
Soil removal25 t dump trucksThe number of trucks is calculated from the excavator cycle
Grading, backfilling, compactionBulldozer, motor grader, soil roller, plate compactorRoller and plate compactor — based on layer thickness and volume
Installation of slabs, trusses, steel structures25 t or 50 t truck crane, crane-manipulator truckLifting capacity is selected by boom reach, not by load weight
ConcretingTruck mixer, 36 m truck-mounted concrete pumpA pump pays off on large volumes and at height
Work at height, facades28 m aerial platformCheaper than scaffolding for short tasks
Site power supply100 kW diesel generatorPower — based on the sum of the equipment's starting currents

Warning The most common mistake when ordering a crane is choosing it by load weight. A 25 t truck crane lifts 25 t only at minimum reach. At a reach of 15–20 m its actual lifting capacity can be several times lower, so a crane is selected by its load chart and the site layout.

How to save: a step-by-step plan

  1. Prepare the work front The site is cleared, access roads are filled, materials and slings are in place, utilities are marked. Any waiting on site is paid downtime.
  2. Combine tasks One truck crane visit for several lifts, one excavator visit for the excavation and utility trenches.
  3. Choose machinery to fit the task Excess lifting capacity or bucket volume costs more and does not always speed up the work.
  4. Coordinate logistics Balance the number of dump trucks against the excavator's productivity so that no machine stands idle.
  5. Negotiate a long-term rate For work lasting a week or more, a per-shift or monthly rate is more cost-effective.
  6. Record the time Keep a waybill or a shift log signed by the responsible person — this prevents disputes at settlement.

Checklist before ordering

  • the type and scope of work are described: cubic metres of soil, weight and dimensions of loads, lifting height;
  • site dimensions, access restrictions, the presence of power lines and neighbouring buildings are known;
  • dates and shift durations are set;
  • it is clear who provides slingers and the person responsible for the safe performance of work;
  • the contract states the rate, mobilisation, conditions for downtime and order cancellation;
  • the procedure for confirming hours worked has been agreed.

Tip If the site needs different machinery — an excavator, dump trucks, a roller, a crane — it is more cost-effective to order it from a single supplier. This makes it easier to synchronise the schedule, and mobilisation can be optimised.

One-off order or long-term rental

The rental format depends on the duration and rhythm of the work. For short tasks — unloading materials, installing a few slabs, digging a trench — an hourly order with a minimum charge is enough. If the machinery is needed every day for several weeks, the hourly rate becomes unprofitable: it is better to agree on per-shift or monthly payment with a fixed number of shifts. It is important to specify in advance how weekends, bad-weather days and work interruptions caused by the client are accounted for.

It is also worth assessing which is more cost-effective for earthworks — renting machinery with hourly payment or ordering the work "by volume" with payment per cubic metre. The second option shifts the risk of low productivity to the contractor but requires an accurate calculation of quantities based on the design.

The most expensive machinery is the one standing idle on site.

How to book

Choose machinery in the special machinery catalogue and submit a request in your personal account with the dates and a description of the work — a manager will clarify the details, confirm the booking and send the contract. All machines work with experienced operators, and if necessary we will put together a set of machinery for the entire stage of work. We operate in Almaty, Astana, Taraz and the regions — office contacts are in the "Contacts" section. If you need not only machines but also the complete execution of works, see our general contracting services.

We will match machinery to your task Describe the scope of work — we will propose the optimal set of machines and a schedule without unnecessary downtime.

Choose machinery

Questions and answers

What is included in the cost of special machinery rental?

As a rule, the operation of the machine with an operator and fuel. Delivery of the machine to the site (relocation) and the minimum shift may be charged separately. Check this before ordering.

What is the minimum shift?

Usually 4–8 hours depending on the type of machinery. For truck cranes and excavators it is more cost-effective to plan work for a full shift.

How do I book machinery for specific dates?

Choose a machine in the "Equipment" section and select the dates in the calendar — days already booked are shown in red. A manager will confirm the booking, and clients with a personal account will see its status online.

Request

Tell us about your project

We will prepare a preliminary estimate and timeline. If you are registered, you can track the request status in your account.

We reply within one business day
Call WhatsApp